000 01690naa a2200241uu 4500
001 6032214392721
003 OSt
005 20190211160722.0
008 060322s2006 xx ||||gr |0|| 0 eng d
100 1 _aMAHESWARI, J. Uma
_923573
245 1 0 _aProject Scheduling using Dependency Structure Matrix
260 _aAmsterdam :
_bElsevier,
_cApril 2005
520 3 _aDependency Structure Matrix (DSM) has been identified as a powerful tool to plan the activity sequences, identify and manage information exchanges. However, its application in scheduling is very limited. So far, DSM has been used to enable critical path calculations by assigning the ‘amount of effort/work done’ as duration to the activities. This paper addresses ‘communication time’, a new concept while estimating the normal project duration.
520 3 _aThe other issue arises, while planning and scheduling compressed projects with DSM. When the activities are overlapped to achieve the compressed duration, there arise two cases – the natural overlap (involving minimum risk) and the forced overlap (involves more risk). This paper focuses on the estimation of natural overlap project duration using DSM. Further, the author also proposes a detailed implementation procedure focusing on the above ideas and is illustrated through an example.
650 4 _aManaging projects
_916897
650 4 _aProcesses and procedures
_923574
650 4 _aScope of work
_923575
650 4 _aTime
_912463
700 1 _aVARGHESE, Koshy
_923576
773 0 8 _tInternational Journal of Project Management
_g23, 3, p. 223-230
_dAmsterdam : Elsevier, April 2005
_xISSN 0263-7863
_w
942 _cS
998 _a20060322
_b1439^b
_cNatália
999 _aConvertido do Formato PHL
_bPHL2MARC21 1.1
_c15060
_d15060
041 _aeng