100 1 _aBROOME, Jon
_91498
245 1 0 _aHow practitioners set share fractions intarget cost contracts
260 _bJ. R. Turner,
_c2002
520 3 _aResearch into target cost contracts has been undertaken at The University of Birmingham to understand the choice of share profiles used in practice. The use of target cost contracts in increasing and the research has shown that share porfiles which vary with the extent of over or under run are more common today than constant share profiles. Seven examples of share profiles used in practice are described and the reason for their choice are explained. These choices are then dicussed in the context of key factors considered when choosing a contract strategy. The use of utility theory proposed by others for determining the share profile is briefly considered and the authors believe its is both insufficiently pragmatic and unable to deal with the complex interactions of the factors which should govern the choice of share profile
650 4 _aContract Strategy
_916795
650 4 _aTarget Cost Contract
_916796
650 4 _aIncentive Contract
_916797
650 4 _aUtility Theory
_916798
700 1 _aPERRY, John
_916799
773 0 8 _tInternational Journal of Project Management
_g20, 1, p. 59-66
_dJ. R. Turner, 2002